Energy Cases 2026: Spark Spread and Capacity Factor
A 500 MW gas plant worked in cents per kilowatt hour, the rate class that doubles the price, and why the capacity factor a plant needs can exceed 100 percent.
- In energy the output price is set by a market, so the lever a case actually has is the gap between that price and the fuel cost of one kilowatt hour.
- On the worked plant, a 1.3 cent spark spread implies a break-even capacity factor of 105.37 percent, which is arithmetic telling you the plant cannot cover its fixed cost at any output.
- At a 50 percent capacity factor the plant needs a 2.74 cent spread, which means a 5.94 cent power price against the 4.5 cents the market pays.
- A 25 percent fall in the gas price is worth $15.33 million a year and a 10 percent heat rate gain is worth $6.13 million, so fuel price moves the result 2.5 times as hard as efficiency.
- EIA puts the 2025 US average at 17.30 cents for residential customers and 8.62 cents for industrial ones, so a blended price per kilowatt hour describes neither.
Most cases hand you a price you can change. An energy case usually does not. Power, gas and crude clear in markets, so the seller takes the price and the only variables left are the cost of producing one unit and how many units the asset produces. That is why an energy structure looks nothing like a consumer goods structure.
The conversion that unlocks an energy case interview
The number an energy prompt gives you is a heat rate, and the number you need is a cost per kilowatt hour. Converting between them is the first thing to get right, and it is two multiplications.
A heat rate is British thermal units of fuel per kilowatt hour of output. A gas price is dollars per million British thermal units. So fuel cost per kilowatt hour equals the heat rate divided by one million, times the gas price.
At a 7,000 Btu heat rate and $4.00 gas, that is 7,000 divided by 1,000,000, which is 0.007, times $4.00, so $0.028 a kilowatt hour. Written the way the industry writes it, 2.8 cents.
Add variable operations and maintenance of 0.4 cents and the variable cost of one kilowatt hour is 3.2 cents. Subtract that from the power price and you have the spark spread, which is the contribution margin of a gas plant under another name. At a 4.5 cent power price the spread is 1.3 cents.
Two habits protect this step. Write the unit beside every figure before multiplying, because Btu, million Btu, kilowatt hour and megawatt hour are four bases and three of them are wrong. And convert megawatt hours to kilowatt hours early, since prices are quoted per kilowatt hour and output is quoted in megawatt hours.
Reading a worked example is not producing one.
Score my answerCosting one plant, and reading the impossible answer
Here is the prompt. Every cost figure in it is ours, posed as an assumption, and a candidate should label their own the same way.
Cardinal Power owns one combined cycle gas plant and wants to know whether to keep it open.
- Nameplate. 500 megawatts.
- Heat rate. 7,000 Btu per kilowatt hour.
- Fuel. $4.00 per million Btu.
- Variable operations and maintenance. 0.4 cents a kilowatt hour.
- Power price received. 4.5 cents a kilowatt hour.
- Fixed cost. $60 million a year, covering the capital charge, fixed maintenance, staff and interconnection.
- Current dispatch. A 50 percent capacity factor, set by where the plant sits in the merit order.
At nameplate, 500 megawatts for 8,760 hours is 4,380,000 megawatt hours. At a 50 percent capacity factor that is 2,190,000 megawatt hours, which is 2.19 billion kilowatt hours.
Contribution is 2.19 billion times 1.3 cents, so $28,470,000. Against $60 million of fixed cost the plant loses $31,530,000 a year.
Now solve for the capacity factor that would break even. Full output contribution is 4.38 billion kilowatt hours times 1.3 cents, so $56,940,000. Divide $60,000,000 by that and you get 105.37 percent.
Do not treat that as an error. It is the answer, and it is the most decisive sentence available: at a 1.3 cent spread this plant cannot cover its fixed cost even running every hour of the year. The recommendation is therefore not about dispatch. It is about the spread, the fixed cost, or closure.
Solving the energy case backwards for a number the client can act on
A capacity factor above 100 percent closes one door and opens the useful one. Hold the 50 percent capacity factor, which reflects where the plant sits in the merit order, and solve for the spread it needs.
$60,000,000 divided by 2.19 billion kilowatt hours is $0.0274, so 2.74 cents. Against the 1.3 cents the plant earns today, it needs more than double.
Translate that into the price the market would have to pay. Variable cost is 3.2 cents, so the required power price is 3.2 plus 2.74, which is 5.94 cents. Against 4.5 cents received, the plant needs 32 percent more than the market gives it.
That single figure reframes the case. Nothing inside the plant closes a 32 percent price gap, so the branches worth spending time on are the ones that change the denominator or the fixed cost. Contract the output at a fixed price above market. Retire the plant and stop the $60 million. Repower it, which resets both the heat rate and the fixed cost. Or bid it into a capacity market, which pays for availability rather than energy and is a different revenue line altogether.
Which sensitivity actually moves the answer
Two levers get proposed in every energy case, and they are not the same size. Test both.
| Scenario | Variable cost | Spark spread | Contribution at 50% | Gain against base |
|---|---|---|---|---|
| Base: 7,000 Btu, $4.00 gas | 3.20c | 1.30c | $28,470,000 | -- |
| Heat rate to 6,300 Btu, $4.00 gas | 2.92c | 1.58c | $34,602,000 | $6,132,000 |
| 7,000 Btu, gas to $3.00 | 2.50c | 2.00c | $43,800,000 | $15,330,000 |
The middle row is a 10 percent heat rate improvement, which is a major capital project. It adds $6,132,000 of annual contribution. The bottom row is a 25 percent fall in the gas price, which the plant does not control at all. It adds $15,330,000.
The ratio is $15,330,000 over $6,132,000, which is exactly 2.5. So at this heat rate the fuel price moves the result two and a half times as hard as a substantial efficiency gain. Neither row reaches the $60 million fixed cost on its own, and saying so is part of the answer.
The engineering reading of this is worth stating plainly. A heat rate gain scales with the fuel price, because the saving is a percentage of a fuel bill. When fuel is cheap, efficiency projects are worth less, which is the opposite of the intuition most candidates bring.
Can you hold an industry case under a clock?
Never blend a regulated and a merchant business in an energy case
Utilities routinely contain both a regulated network and a merchant generation arm, and their economics are unrelated. A regulated network earns an allowed return on a rate base set by a commission, so its revenue is a function of invested capital and its volume risk is limited. A merchant generator earns a spread, so its revenue is a function of a market price it does not set.
A blended margin across the two produces a number that describes neither, and it is the most common structural error on this case type. Split them in your first branch and keep them split.
The Energy Information Administration shows how far a blended price can mislead even inside one business. Its table 5.3 gives 2025 US averages of 17.30 cents per kilowatt hour for residential customers, 13.41 cents for commercial, 8.62 cents for industrial and 13.63 cents for all sectors, checked 30 September 2026 at eia.gov. The residential average is 2.01 times the industrial average.
So when a prompt says customers pay a given number of cents, ask which class. The same utility serving the same grid earns roughly double per kilowatt hour from a household compared with a factory, and the difference is cost of service and rate design rather than margin.
For the asset side, the Federal Reserve's release of 18 September 2026 reports the following. "The operating rate for mining rose 0.1 percentage point to 86.3 percent, and the operating rate for utilities increased 1.1 percentage points to 71.3 percent", published at federalreserve.gov. The same release puts the long-run utilities average at 84.0 percent, so the sector was running 12.7 points below its own normal rate.
Ask which horizon an energy case recommendation is measured on
Before recommending anything, ask what bar the client underwrites. Published cases disagree sharply, and an energy asset has a life long enough that the disagreement changes the answer.
Oliver Wyman's own practice case is the clearest example in print. An Indian gas operator considers distributing drinking water, and the published lines are "Annual revenue: Rs. 750,000,000, assuming 300 operational days per year" and "Total annual costs: Rs. 575,000,000 or 57.5 crore". Recomputing from the stated inputs: 250,000 kiloliters a day across 300 days is 75 million kiloliters, at 10 rupees that is 750 million rupees or 75 crore, variable cost at 5 rupees is 375 million or 37.5 crore, plus 20 crore of fixed cost gives 57.5 crore, so annual profit before tax is 17.5 crore. The firm's three lines all reconcile.
Then it refuses the project, because entry "does not align with the client's investment criteria for a five-year payback period", checked 30 September 2026 at oliverwyman.com. A profitable business, declined on a time criterion.
Commodity risk is why that convention exists here. Gulf Coast jet fuel spot went from $2.024 a gallon in August 2025 to $3.724 in August 2026, a rise of roughly 84 percent inside twelve months, published at eia.gov. A five year payback on an asset exposed to moves of that size is a different risk from a five year payback on a regulated network.
Where the points go on a generation case
The scheme below is ours. We read the weights out of the grading code in src/lib/grading, and no firm publishes a marking scheme for a case interview, so these are our dimensions rather than anyone's official ones.
- Answer40
- Working25
- Interpretation20
- Units15
| Structuring | Coverage 45 · Separation 25 · Depth 20 · Concision 10 |
|---|---|
| Idea generation | Breadth 30 · Buckets 30 · Specificity 20 · Prioritisation 20 |
| Market sizing | Scope 25 · Assumption chain 30 · Arithmetic 25 · Sanity check 20 |
| Exhibits | Observation 25 · Implication 25 · So what 30 · Next test 20 |
| Synthesis | Answer first 35 · Evidence 25 · Risk 20 · Next step 20 |
Units carry 15 of the 100, and on an energy case that line is the most exposed of the four. Btu against million Btu is a factor of a million. Megawatt hours against kilowatt hours is a factor of a thousand. Cents against dollars is a factor of a hundred. Three conversions, each one silent in the total and fatal in the conclusion.
Interpretation carries 20, and the 105.37 percent capacity factor is the case in miniature. Reporting the figure is a result. Saying that a break-even capacity factor above 100 percent rules out every dispatch answer and forces the conversation onto fixed cost is the answer.
Answer carries 40, and Working 25. On a chain with three conversions, showing the intermediate figures is what lets an interviewer follow you: 0.007, then 2.8 cents, then 3.2 cents, then 1.3 cents.
Run the arithmetic against a clock with the math drill, and the volume algebra with the break-even calculator. Both are free and need no sign-in. Our weights and the reasoning behind each one sit on how an answer is assessed. For the neighboring capacity heavy sectors, see airline cases and automotive cases. For the discounting question an asset with a thirty year life raises, see NPV in cases.
Where the public record runs out
We looked for a first-hand candidate account of an energy case and found none we can cite. Reddit refuses connections from this network, and no video transcript tooling was available in the session. Oliver Wyman publishes two consultant profiles and neither discusses its six practice cases. McKinsey publishes two recruiting blog posts with the same silence. Competitor preparation blogs cover energy cases at length and are not citable sources.
Five figures a case needs are not published anywhere we could reach. Nobody publishes the heat rate of a named plant, so the 7,000 Btu figure is ours. Nobody publishes fixed cost per megawatt of capacity, so the $60 million is ours. The Energy Information Administration publishes average prices paid by customer class and not the wholesale price any particular generator receives, so the 4.5 cents is ours. Capacity market clearing prices exist in public auction results, and we did not read them, so this page does not quantify that branch. And no firm publishes a hurdle rate for approving a generation asset, which is exactly why the question above is asked rather than assumed.
See your answer scored, dimension by dimension.
Reading a worked example and producing one are different skills. Work a full case and see it scored, dimension by dimension.
Sources
Primary sources only: the firm, the test vendor, or the institution concerned. Each carries the date we last read it.
- eia.gov/electricity/monthly/epm_table_grapher.php?t=epmt_5_3average price of electricity to ultimate customers by end-use sector, annual figures for 2020 and 2025, release date 24 September 2026checked 2026-09-30
- federalreserve.gov/releases/g17/current/default.htmthe utilities operating rate for August 2026 and its distance from the long-run average, quoted from the release textchecked 2026-09-30
- oliverwyman.com/careers/entry-level/interview-preparation/oil-gas-price-strategy-case-interview.htmlthe published energy case whose model answer refuses a profitable business on a five-year payback criterion, with the revenue and cost lines behind itchecked 2026-09-30
- eia.gov/dnav/pet/hist/LeafHandler.ashx?n=pet&s=eer_epjk_pf4_rgc_dpg&f=ma dated example of how far a refined fuel price moves inside twelve months, used to size the commodity risk in the recommendationchecked 2026-09-30
Edits the firm and case guides on this site. Reads each claim about a recruiting process back to the firm's own page before it is published, keeps the source ledger dated, and owns the corrections.
How this guide was made
- Written against a published editorial process, not from memory. Every claim about a firm's process is either linked to that firm's own page or absent. We say what we could not verify rather than filling the gap.
- Each page carries a dated source ledger, below. When a firm changes a programme or a deadline, the date tells you how far to trust what you just read.
We look for first-hand candidate accounts for every firm guide. Where we found none we could source, the page says so and carries the firm's own words instead. Nothing here is dressed up as testimony, and if your own experience contradicts what you read, tell us and we will correct it and date the change.
Something wrong or out of date here? Tell us and we will correct it and date the change.